Customer challenges
- Natural gas flaring represents a lost economic opportunity but is also a major source of greenhouse gas emissions
- Gas was being flared at multiple production sites due to the unavailability of the appropriate processing infrastructure
- Our customer had a solution but in review was considered unreliable and sub economic
Expro Excellence
- Expro undertook a detailed comparative study to find an economic alternative to gas flaring
- The resulting solution utilised a gas to power compressor at 10 sites
- Expro delivered, installed and commissioned the compressors within 32 weeks (contract award to first gas)
Value to client
- Fast-track equipment delivery enabled customer to obtain reduced flared gas gains and optimise production to meet export commitments and increase life of field
- Produced Gas to Power compressors were utilised which significantly reduced OPEX costs at the 10 sites significantly increasing customers ROI
- Customer reduced Green House Gas Emissions across the 10 sites by up to 10,000 Tons CO2e per day