Innovative well testing delivers fast-track production solution
Customer challenges
  • Expro's customer was replacing its temporary platform ( an existing drilling rig) with a newly fabricated platform to achieve a 12,000bbls/day and 6.5mmscf/day production objective
  • Expro was approached to provide a fast-track solution for delivering production facilities - leveraging existing contractual arrangements
  • A solution was required which was flexible, cost effective and allowed the client to significantly accelerate their production delivery
Expro Excellence
  • Expro designed a bespoke solution that modified existing well test assets to form the basis of a production system including: Separators, process heaters, tanks, pumps and flare booms
  • This was designed, delivered and operated under a single existing contract allowing the customer to quickly monetise production from a marginal field
  • A coordinated approach from both the client and their designated platform engineering company, ensured the technical requirements were achieved and the interface perfectly aligned
  • Production was continuously monitored and reported using Expro's web based real-time 'data to desk' transmission service. This allowed the client to optimise production rates further by monitoring well behaviours and flow rates, informing them on the best approach to bringing optimal wells into the production facility
Value to client
  • Expro's solution allowed the client to deliver the production nearly two years ahead of schedule when compared to a traditional EPC (Engineering, Procurement, Installation and Commissioning) approach
  • A dedicated project team with direct access to the 24-7 operations and maintenance support crew ensured the project was commissioned on schedule and with zero HSE incidents
  • The project management team were aligned with both client and their other contractors to expedite the plan enabling the client to release the drilling rig per plan, successfully securing the project cost target
Contact

Innovative well testing delivers fast-track production solution

In Brief
Innovative well testing application delivers economical fast-track production solution
Product Line
  • Well Testing
Region
Middle East And North Africa
Customer challenges
  • Expro's customer was replacing its temporary platform ( an existing drilling rig) with a newly fabricated platform to achieve a 12,000bbls/day and 6.5mmscf/day production objective
  • Expro was approached to provide a fast-track solution for delivering production facilities - leveraging existing contractual arrangements
  • A solution was required which was flexible, cost effective and allowed the client to significantly accelerate their production delivery
Expro Excellence
  • Expro designed a bespoke solution that modified existing well test assets to form the basis of a production system including: Separators, process heaters, tanks, pumps and flare booms
  • This was designed, delivered and operated under a single existing contract allowing the customer to quickly monetise production from a marginal field
  • A coordinated approach from both the client and their designated platform engineering company, ensured the technical requirements were achieved and the interface perfectly aligned
  • Production was continuously monitored and reported using Expro's web based real-time 'data to desk' transmission service. This allowed the client to optimise production rates further by monitoring well behaviours and flow rates, informing them on the best approach to bringing optimal wells into the production facility
Value to client
  • Expro's solution allowed the client to deliver the production nearly two years ahead of schedule when compared to a traditional EPC (Engineering, Procurement, Installation and Commissioning) approach
  • A dedicated project team with direct access to the 24-7 operations and maintenance support crew ensured the project was commissioned on schedule and with zero HSE incidents
  • The project management team were aligned with both client and their other contractors to expedite the plan enabling the client to release the drilling rig per plan, successfully securing the project cost target