Customer challenges
- Long conductor wait on cement of ~15-19 hours on offset wells
- Previous time spent drilling out 20" conventional SSR plug shoetrack
Expro Excellence
- QuikCure® reduced the conductor WOC and SeaCure® provided zero shoetrack solution for optimized drill out of both 30" and 20" shoes
- QuikCure® rapid cement hydration heat sweep enabling the drilling of 26" hole just 13 hours after the end of the conductor cement job – in comparison to a previous WOC of 25 hour
Value to client
- Reduced conductor WOC time to 5.5 hours with data capture evidence to show cement hydration at just 3 hours after placement of QuikCure® heat sweep
- Reduced 20" shoe drill out time to 45 minutes
Saved rig time by utilizing the same simple cementing stand for conductor and surface casing cement jobs
SeaCure® system moves hydraulic seal for cement placement and displacement to the shoe removing reliance on ball valve and running tool seals