The client needed to install three 30” conductor strings to depths below the shallow water flows at 26’ in Bouillante, Guadeloupe, a remote island in the Caribbean, where conventional drill in methods would not work
The main challenge with driving the conductor to the desired penetration depths on land was utilizing a construction crane prior to the drill rig arriving
Another challenge was the coordination of remote logistics and mobilizing the necessary equipment and personnel to a location with limited drilling infrastructure
Expro Excellence
Expro utilized a specially designed land frame to support the conductor vertically during initial operation
Expro’s personnel provided expert knowledge to the customer throughout the project
Expro provided the welded pipe, fabricated drive shoes for each of the three planned wells and welding support
All equipment was mobilized from our Lafayette office along with experienced personnel
Expro installed the three conductor strings at 92’, 76’ and 34’ respectively
Expro successfully delivered the project with limited access to logistics and infrastructure
Value to Client
By utilizing our 60+ years of conductor installation methods we were able to safely install the three wells offline prior to the drilling rig mobilization
Utilizing the customer’s soil boring data, we performed a drive prediction analysis to determine the hammer size and the projected penetration based on pile geometry
Expro provided on the spot advice to the client to improve their operations