Customer challenges
- An independent operator in West Africa needed to generate early cash to fund investment in its long-term production facilities
- The Regulatory body requested well performance data before authorizing the start of commercial production
- The temporary facility was to be operated and maintained until the permanent process facility was installed and commissioned
- The safety challenges associated with SIMOPS – i.e. installation of the permanent facility whilst continuing to produce hydrocarbons via the temporary facility
- Remote location: Difficult terrain to access the site and then install equipment
Expro Excellence
- Expro mobilized and installed a well testing package that was configured such that additional equipment could be tied-in to continue production at increased rates of up to 10,000 bpd once the well test was complete
- Production commenced with a single train of standard well test equipment and was subsequently increased with the addition of a second train installed in parallel
- Stabilized crude oil was transferred into the client’s tank farm, from where it was finally exported to an FSO moored offshore
- Although the site was not easily accessible and represented a logistical challenge the in-country team and Expro’s logistics resources ensured a scheduled and safe delivery of the facilities
- The Expro central Production Solutions Product line together with the Expro Nigeria team managed the complete scope from contract award with engineering design, procurement, logistics, installation, commissioning, and start-up
Value to client
- Installation of the temporary equipment was engineered such that it would not hinder the preparation of foundations and installation of the permanent facility; thereby providing excellent safety performance during SIMOPs
- The piping between the process equipment and production manifold was engineered and designed to minimize the suspension of production when switching from the temporary equipment to the permanent facility; thereby, optimizing uptime, and maximizing production and cash flow for the client
- Expro team provided the O&M services during the initial operation phase of the permanent facility and trained the client’s staff until they took over the operation of the plant
- Zero unplanned shut down, resulting in 100% uptime during operation by Expro team