Expro Excellence
CoilHose
CoilHose operation in Malaysia completed within 12 hours
Customer challenges
  • Expro's customer had requested mobilisation of conventional coil tubing as a contingency to lift the overbalance cushion in a newly completed well
  • Operations were planned to be conducted on the critical path with the use of a drilling rig
  • Incumbent supplier was not able to provide a coil tubing package within the requested time frame and therefore posed a potential delay to the work scope which would impact delivery of the entire project
  • Expro's CoilHose was fast-track mobilised to provide the required solution
Expro Excellence
  • Expro provided a proposed engineered solution with its latest 3/4" OD CoilHose Light Well Circulation System
  • Equipment was prepared and mobilised to the region within 21 days where a successful Site Integration Test (SIT) was completed prior to mobilisation to the rig
  • Key interfaces with the rig and other key suppliers were successfully managed
  • Expro delivery met the customer expectations and the project continued without delay
Value to client
  • Overall delivery of the well without impacting the project timeline
  • Equipment was mobilised on a scheduled vessel  which removed the requirement for a chartered vessel that would normally be required for conventional coil tubing
  • CoilHose has reduced complexity, footprint and weight compared to traditional coil tubing equipment which allowed for optimum planning through to operational execution and de-mob
  • Like for like operational timings were significantly reduced and performed with a multi-disciplined reduced POB
  • As a result, the CoilHose operation reduced well over 75% of the like for like operational CO2e emissions
Contact

CoilHose operation in Malaysia completed within 12 hours

In Brief
Expro delivers first CoilHose operation in Malaysia to support well test operation
Product Line
  • CoilHose
Region
Asia-Pacific
Customer challenges
  • Expro's customer had requested mobilisation of conventional coil tubing as a contingency to lift the overbalance cushion in a newly completed well
  • Operations were planned to be conducted on the critical path with the use of a drilling rig
  • Incumbent supplier was not able to provide a coil tubing package within the requested time frame and therefore posed a potential delay to the work scope which would impact delivery of the entire project
  • Expro's CoilHose was fast-track mobilised to provide the required solution
Expro Excellence
  • Expro provided a proposed engineered solution with its latest 3/4" OD CoilHose Light Well Circulation System
  • Equipment was prepared and mobilised to the region within 21 days where a successful Site Integration Test (SIT) was completed prior to mobilisation to the rig
  • Key interfaces with the rig and other key suppliers were successfully managed
  • Expro delivery met the customer expectations and the project continued without delay
Value to client
  • Overall delivery of the well without impacting the project timeline
  • Equipment was mobilised on a scheduled vessel  which removed the requirement for a chartered vessel that would normally be required for conventional coil tubing
  • CoilHose has reduced complexity, footprint and weight compared to traditional coil tubing equipment which allowed for optimum planning through to operational execution and de-mob
  • Like for like operational timings were significantly reduced and performed with a multi-disciplined reduced POB
  • As a result, the CoilHose operation reduced well over 75% of the like for like operational CO2e emissions