Expro Excellence
Well Testing
Expro’s modular well test package cuts costs with faster setup and flexibility
Customer challenges
  • A North Sea operator engaged Expro to address challenges on a delayed field development project with aggressive timelines for achieving the first oil
  • The operator faced the following critical issues:
  • Project delays required accelerated cleanup and production testing to extend the life of subsea wells while avoiding costly interventions
  • The existing rig's deck loading exceeded design limits, yet modifications to the rig were not feasible without jeopardizing the project's schedule
Expro Excellence

Expro developed an innovative modular clean-up package to meet the client’s requirements without rig modifications

Rig Survey and Preliminary Design:

  • Conducted a comprehensive survey of the rig and created a detailed design with loading calculations to ensure adequate weight distribution of the modular package across the rig deck

Modular Engineering Approach:

  • Constructed a false deck in modular sections to reduce complexity and expedite installation. Ensured integration of flow lines, relief lines, power, and air systems before the arrival of the main clean-up equipment

Streamlined Installation Process:

  • Pre-installed sea fasteners with a three-person crew as an offline activity, minimizing on-site disruption. Delivered and installed the false deck in four sections, leveraging pre-installed fasteners to enable rapid setup. Reduced crane operations and manual handling, ensuring a safer and more efficient installation

Collaborative Execution:

  • Worked closely with the client throughout, including system integration tests and final approvals in Stavanger
Value to client
  • Project delays were addressed enabling an accelerated well clean-up without any rig modifications
  • Optimal safety and efficiency were achieved through collaborative design and streamlined installation
  • Aggressive timelines for achieving first oil were met
Contact

Expro’s modular well test package cuts costs with faster setup and flexibility

In Brief
Expro's modular flow-back package ensured timely first oil, enhanced efficiency, cost savings, and improved safety for a North Sea operator
Product Line
  • Well Testing
Region
Europe and Sub Saharan Africa
Customer challenges
  • A North Sea operator engaged Expro to address challenges on a delayed field development project with aggressive timelines for achieving the first oil
  • The operator faced the following critical issues:
  • Project delays required accelerated cleanup and production testing to extend the life of subsea wells while avoiding costly interventions
  • The existing rig's deck loading exceeded design limits, yet modifications to the rig were not feasible without jeopardizing the project's schedule
Expro Excellence

Expro developed an innovative modular clean-up package to meet the client’s requirements without rig modifications

Rig Survey and Preliminary Design:

  • Conducted a comprehensive survey of the rig and created a detailed design with loading calculations to ensure adequate weight distribution of the modular package across the rig deck

Modular Engineering Approach:

  • Constructed a false deck in modular sections to reduce complexity and expedite installation. Ensured integration of flow lines, relief lines, power, and air systems before the arrival of the main clean-up equipment

Streamlined Installation Process:

  • Pre-installed sea fasteners with a three-person crew as an offline activity, minimizing on-site disruption. Delivered and installed the false deck in four sections, leveraging pre-installed fasteners to enable rapid setup. Reduced crane operations and manual handling, ensuring a safer and more efficient installation

Collaborative Execution:

  • Worked closely with the client throughout, including system integration tests and final approvals in Stavanger
Value to client
  • Project delays were addressed enabling an accelerated well clean-up without any rig modifications
  • Optimal safety and efficiency were achieved through collaborative design and streamlined installation
  • Aggressive timelines for achieving first oil were met
Contact

For further information, please contact:

[email protected]