Challenge
A West Texas operator needed to isolate over 2,300ft corroded casing due to water flow in their West Texas well. Multiple attempts to squeeze cement had failed and the customer needed a permanent means to isolate this problematic corroded casing section.
Solution & Achievement
A Re-Line MNS 4.25” x 5.5” 17# system was chosen as it features no shoe drill-out (MNS = Mechanical No Shoe) and its larger post expanded ID which allowed a specific sized large OD ESP to be run afterwards.
Prior to running the Re-Line MNS, Coretrax were able to provide the full well bore clean out using the Coretrax ORIGIN mechanical clean out and debris recovery tools, whilst at the same time drifting the casing to ensure the path ahead was clear before running the patch.
Having the Well Bore Clean Up / diagnostic run, performed by the same company that runs the patch not only saves time and trucking, but also means less personnel are sent to the rig.
The Re-line MNS patch was run and tested with no issues at all, and the customer was delighted to have the well back on track so quickly and efficiently.